The pillar of cement cracking due to corrosion of reinforcement in columns or force on other objects. The impact broke the pole. We can repair. This marks the first crack on their own.
Solution - Use concrete nails or extracted. I broke the head or use a hammer to break. Pune to open more.
The break is over.
- After a steel brush Remove dust that blocked out. Free from dirt, dust, debris, oil, grease stains without disruption were cleaned with water.
- The water mixed cement. The technical term is called lime water liquid or cream and pour it in the drain. O flow more grip. Which prevents disintegration.
- Cement mixed with 1 to 2 parts clean sand mixed with water, gently knead the mixture until thick and sticky. But do not let the liquid.
- Import of cement to cut with a steel trowel. On the concrete preparation. A depth of about 1 to 1.5 cm in diameter. Leave it for about 10 minutes, I began to see that the cement plaster damp enough to cut up to about an inch .1.5 do this until the skin is always pillar cement plaster so as to facilitate the cutting face is always pillar and a square pillar.
- Cover with a damp cloth about 1-2 work days, after which the water is wet or covered with a damp cloth or wet for about 7-15 days, will be back poles beautiful.
The cracks in the pillars that mark the oblique Junction pole or beam. Or maybe it's the concrete surface.
Reinforcement in columns. The expert should mark the beginning of the post, you can lose the ability to act is not the weight of the building. Which is detrimental to the residents in the building.